When
Projects Fail and GO legal!
Sadly, seven out of ten projects fail. Some lead to
customers taking their IT Partner (System Integrator, Consultancy Firm et al)
to court to claim damages. The outcomes of such cases are rarely reported and
many lead to compromise agreements. Obviously, both parties will not wish to
‘hand their dirty washing out in public’.
For the Project Manager community we never get to learn the
lessons from such legal cases. So based upon my experience over the past ten
years, I calculate that three projects out of every fifteen ended up in court.
So what went so badly wrong to land the respective parties
in a court of law defending their respective positions?
1.
The
respective parties expectations of each other failed to align and were only
fully exposed at the end of the implementation. Sadly, often too late to
address the underlying issues. I have witnessed organisations failing to take
ownership and seemingly leaving it to the implementation partner to shoulder
all the responsibilities for getting the project live. Hard to believe in 2014
when you would have assumed organisations are project savvy.
·
There is a case going through the courts now
where an organisation requested significant customisations to an ERP solution
and then blamed the implementation partner for poor quality code after the
solution went live! So what went wrong (if anything) in the testing stages and
perhaps more importantly why did the organisation fail to adopt the solution?
·
They
failed to adequately invest in internal business project resources to support
the key stages of testing and transition into live running
·
They
failed to acknowledge the likely business impacts and then invest in business
change resources to help the employees adopt the new ways of working enabled by
the solution
2.
The solution
fails in testing, possibly UAT and heavens forbid fails in live running.
The solution fails for one or many reasons and doesn’t do what it says on the
tin!
·
There is a case where a large organisation
pulled the plug on a service management solution at the UAT stage having invested
over £20m when they discussed that the ERP vendor had previously advised their
System integrator that the proposed solution would not work a year earlier!
·
Avoid the bleeding
edge projects!
·
Work closely
with the application provider and their design/development team
3.
The client
bought a standard application solution but had to demand customisations
that extended the scope of the project and led to major project overruns on
time and cost
·
A recent case in the local government sector saw
a consultancy firm challenged in the law courts for failing to manage the
delivery of the solution with all the required customisations within the agreed
budget (revised many times). Ironically, the consultancy firm had produced the
original business case detailing a cost of implementation which the Council
approved but then three years later and two behind schedule the cost had
tripled. Why did they get it so wrong? They took a standard approach to delivering
an ERP solution without realising the client had significant requirements that
had not been fully identified, specified and validated
o
Do the
basics right!
o
Define
your business requirements, document and valid them with your key managers and
SME’s, who own them during the implementation lifecycle and beyond
o
Avoid the
temptation to go with a template solution or process flow accelerators without
stamping your organisation mark all over them!
No comments:
Post a Comment